Flood betterment works progressing across the Gannawarra
Published on 28 September 2026
Residents and motorists are benefiting from works across the Gannawarra that are upgrading Council-managed roads, drains and other infrastructure to reduce the risk of disruptions to services and transport connections during future flood events.
Last month’s minor flooding of the Avoca and Loddon rivers saw flood betterment projects at Dingwall, Tragowel and Quambatook utilised for the first time, with new culverts enabling roads to reopen earlier than previously following the receding of floodwaters.
The works were completed as part of Council’s flood betterment project, which aims to improve the resilience and reliability of flood-affected road infrastructure by enhancing floodways damaged during previous flood events and reducing the impact of future flooding on local communities and road users.
“The past few weeks and the 2022 floods highlighted how important it is for residents to remain connected to their communities, especially during times of natural emergencies,” Gannawarra Shire Council Chief Executive Officer, Geoff Rollinson said.
“The improvements at Dingwall, Tragowel and Quambatook, as well as future works, would not have been possible without $1 million in funding from the Federal and State Governments under the Disaster Flood Recovery Arrangements Council Priority Betterment Program, which Council appreciates.”
Works at the Kenny Road floodway, Kerang East, remain a priority, with Council preparing to remove retained water from the area following increased flows along Pyramid Creek before construction resumes.
“We are currently planning to pump out the retained water at the Kenny Road floodway area and allow the site to dry out before continuing with construction works,” Mr Rollinson said.
“At this stage, we expect that process will take approximately another four weeks, however this timeframe remains subject to weather conditions and the condition of the site.”
Council remains committed to delivering the flood betterment works as quickly as possible while ensuring the long-term success of the project.
“While we appreciate the community’s patience, it is important that ground conditions are suitable before we undertake major works. Taking the time to prepare the site properly will help ensure the best possible outcome for residents and road users,” Mr Rollinson said.
Planning is also continuing for improvement works at the Suttie Road floodway, Quambatook, however recent river conditions have created further delays, with the project now expected to commence early next year.
“The Suttie Road floodway is still holding water due to the recent rise in the Avoca River level, making it difficult to predict an exact commencement date at this stage,” Mr Rollinson said.
“Despite these challenges, we remain committed to delivering these important infrastructure improvements and strengthening the resilience of our local road network for years to come.”
Updates regarding improvements at both sites will be provided via Council’s website, Gannawarra News, Gannawarra Connect and Council’s Facebook page.
TOP: The installation of new infrastructure at the Kenny Road, Kerang East floodway has been delayed following increased flows along Pyramid Creek.